December 2023 - Short-term Full Closures of Richmond Road Between McEwen Avenue and New Orchard Avenue
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, Richmond Road will be fully closed to traffic travelling between McEwen Avenue and New Orchard Avenue for the pouring of concrete. Motorists will be detoured along Ambleside Drive. The road closure is planned to be in place for three Saturdays in December. Each pour requires 10 to 15 hours to complete as well as to stage delivery vehicles, cranes, and concrete trucks. Please note that concrete pours must be performed continuously until completed to ensure the quality of the concrete. Crews will work to complete the required work as quickly as possible and will re-open Richmond Road to eastbound traffic earlier than the scheduled times listed in this notice whenever possible.