July 17 to the end of August - Richmond Road at MacEwen Avenue - Night Work
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, crews and equipment will be working overnight on utility installations at the Richmond Road and MacEwen Avenue intersection.
What:
Night work is required at the Richmond Road and MacEwen Avenue to advance deep stormwater sewer pipes. Excavation, hauling and pipe installation will be the primary scope of work.
When:
Wednesday, July 17 until the end of August. Monday to Saturday: 10:00 p.m. to 7:00 a.m. Sundays and Statutory Holidays: 10:00 p.m. to 9:00 a.m.
Why:
To complete critical utility work that is time sensitive and/or required during off-peak hours.
Where:
Richmond Road at MacEwen Avenue.
Anticipated Impacts
Noise and vibration from crews and heavy equipment may be expected.
All construction vehicles and equipment, working overnight will be equipped with broadband back-up alarms. Trucks use approved haul routes and workers and contractors park in designated parking areas.
Generators are required to run equipment in the tunnels. When possible, generators are wrapped in noise barriers.
Site lighting for overnight work is required to maintain safe working conditions for workers. The use of lights will be minimized where possible and special attention paid to ensure that it is not impacting nearby residences.
The City of Ottawa thanks residents for their patience as we work to complete these construction activities.
The safety of the public and workers is paramount,
and we thank you for your patience during construction.
Accessibility
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
Ward 7 Night Work Summary Distribution List
A weekly summary of nightwork providing greater detail as to type and location of activities, is shared at the outset of each week. If you would like to receive the Ward 7 Weekly night work summary, please email stage2@ottawa.ca to be added to the distribution list.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at octranspo.com/o-trainx and select updates for “New Orchard Station”, “Sherbourne Station” and/or “Kichi Zibi Station”. Nightwork associated with Richmond Road Complete Streets will be communicated through the “Richmond Road Complete Streets” option.
For other accommodations, or questions, please contact:
Stage 2 Team
Stage2@Ottawa.ca
Rail Construction Program,
City of Ottawa
octranspo.com/o-trainx
The construction work outlined in this notice is subject to change. Work may be delayed
or extended due to weather or other unforeseen circumstances.